Model Unit Construction Begins

Things are moving along at Beach Houses! The construction of the highly anticipated model Beach House is underway. This two-bedroom Beach House will showcase the environmentally friendly designs of the entire project.

On Monday, August 20th, 2012, The Crane’s construction team poured the foundation for the model unit. After an initial setback presented by heavy rain falls, the team still managed to lay the brickwork up to the ground floor slab.

The team is currently installing the below slab drainage which will be followed by the installation of concrete blinding and electrical services. In the coming weeks, the team expects to complete the installation of the ground floor slab.